Missile Site 345 kV Substation

Quick Facts

  • Estimated cost: $15.5 million
  • Proposed in-service date: January 2013
  • Maps: Project Map
  • Factsheet: Project Summary

The proposed project consists of a new 345-kV substation expansion being constructed jointly with the Pawnee-Smoky Hill 345-kV transmission project.

Regulatory Documents